Starting July 1, 2026, the requirements for new data centers will become much more specific.
Under Section 11 of the EnEfG, two new requirements essentially apply to data centers that begin operations on or after this date:
- Energy Efficiency Based on the PUE: New data centers must achieve a PUE of no more than 1.2.
- Reuse of Energy/Waste Heat: In addition, a minimum percentage of reused energy must be demonstrated: 10% as of July 1, 2026; 15% as of July 1, 2027; and 20% as of July 1, 2028.
In my view, however, what matters is not just that these requirements are coming, but what they mean for planning practice.
This significantly shifts the focus in the data center environment:
- Energy efficiency is becoming a key metric for verification
- Waste heat recovery must be considered earlier in the planning process
- thermal considerations become the basis for planning, rather than a factor for later optimization
This is precisely why simulation is becoming increasingly important. Those who wait until late in the process to verify whether a design actually meets the requirements risk having to make design changes, retrofits, and incurring unnecessary additional costs.
From a technical perspective, this is the real change: Regulatory requirements are having a greater impact on the early concept and planning phases.
If you’re currently working on a data center project and want to understand the new requirements from a technical perspective, I’d love to hear from you!
Jannick Höper
Managing Partner at LIST Eco